| Section | Description | Qty | Unit | Amount ex GST |
|---|---|---|---|---|
| Concrete |
Concrete slab preparation
Prepare for a new concrete floor including set-out, base preparation and forming as needed. Final slab area to be confirmed. |
1.00 | m2 | $0.00 |
| Concrete |
Concrete supply and place
Supply and place concrete floor for the greenhouse repair works. Allow for slab size once dimensions are known. |
1.00 | m2 | $0.00 |
| Demolition |
General demolition labour
Remove existing fittings, linings or fixtures |
1.00 | hour | $1,080.00 |
| Demolition |
General demolition labour
Allowance to strip out and remove the existing shoddy shed elements ready for repair and rebuild works. Confirm what is to be retained versus removed. |
1.00 | allowance | $0.00 |
| Framing |
Timber wall framing
Supply and install standard timber framing |
20.00 | m2 | $2,430.00 |
| Framing |
Timber wall framing
Supply and install timber wall framing associated with the shed/greenhouse repair. Builder to confirm framing extent and condition of existing structure. |
1.00 | m2 | $0.00 |
| Framing |
Structural timber beam allowance
Allowance for any additional structural timber required to support the repair, including roof framing interfaces. Use as a provisional allowance only if required. |
1.00 | allowance | $0.00 |
| Framing |
Ceiling framing / battens
Supply and install framing or battens to suit the truss roof and roof lining/support requirements. Confirm roof type, span and any lining requirements. |
1.00 | m2 | $0.00 |
| General |
Waste disposal allowance
Skip bin or waste removal allowance |
1.00 | each | $420.00 |
| General |
Materials allowance
Allowance for miscellaneous materials not otherwise captured in the estimate. Keep as a small contingency for minor items. |
1.00 | allowance | $0.00 |
| General |
Contingency allowance
Provisional allowance for unforeseen issues uncovered during repair of the existing shed structure. Use at builder discretion; do not assume full use. |
1.00 | allowance | $0.00 |
| Hardware |
Fixings and fasteners allowance
Allowance for fixings, nails, screws, brackets and general hardware required for the repair works. Adjust if stainless or specialty fixings are needed. |
1.00 | allowance | $0.00 |
| Preliminaries |
Project management allowance
Allowance for coordinating the greenhouse repair works, ordering materials and managing site activities. Keep builder in control of scope and sequencing. |
1.00 | allowance | $0.00 |
| Preliminaries |
Site setup allowance
Allowance for basic site setup for repair works including access and protection of work area. Confirm any access constraints at the Carterton site. |
1.00 | allowance | $0.00 |
| Preliminaries |
Travel / mobilisation allowance
Allowance for travel to site and mobilisation of labour, tools and materials. Allow for small-job mobilisation only. |
1.00 | allowance | $0.00 |
| Roofing |
Corrugated iron roofing
Supply roofing material suitable for the greenhouse/shed repair. Final roof area to be confirmed. |
1.00 | m2 | $0.00 |
| Roofing |
Corrugated roofing installed
Install corrugated roofing to the repaired truss roof structure. Allow subject to roof access and condition. |
1.00 | m2 | $0.00 |
| Roofing |
Roof flashing allowance
Allowance for flashings required to weatherproof roof junctions and edges. Quantity to be confirmed on site. |
1.00 | m | $0.00 |
| Roofing |
Spouting / guttering installed
Install spouting or guttering if required to suit the repaired shed/greenhouse. Include only if the scope requires water collection or diversion. |
1.00 | m | $0.00 |
| Site Works |
Ground preparation
Prepare the site for the new concrete floor, including clearing and levelling as required. Quantity to be measured once floor size is confirmed. |
1.00 | m2 | $0.00 |
| Subcontractors |
Engineering allowance
Allowance only if structural advice or engineering input becomes necessary for the truss roof or concrete floor scope. Only include if needed; builder to decide. |
1.00 | allowance | $0.00 |
| Waste |
Waste disposal allowance
Allowance for disposal of demolition waste and offcuts arising from the repair works. Confirm bin size and disposal requirements. |
1.00 | allowance | $0.00 |
This quote is based on the information available at the time of preparation. Any additional work, hidden damage, changes in scope, council requirements, engineering requirements, or client-requested variations may be quoted separately.
Payment is due as agreed in writing. Variations and additional work may be invoiced separately.
Bank Account: 02-0500-00123456-00
Please confirm acceptance of this quote in writing before work begins.