Project management allowance
Preliminaries |
Qty 1.00 allowance
|
$375.00 |
|
|
|
|
$375.00 |
$0.00 |
|
|
Travel / mobilisation allowance
Preliminaries |
Qty 3.00 allowance
|
$225.00 |
|
|
|
|
$225.00 |
$0.00 |
|
|
Trenching excavation
Site Works |
Qty 10.00 hour
|
$750.00 |
|
|
|
|
$543.75 |
$-206.25 |
|
|
Replace piping allowance
Plumbing |
Qty 1.00 allowance
|
$225.00 |
|
|
|
|
$212.00 |
$-13.00 |
|
|
Digger hire allowance
General |
Qty 3.00 allowance
|
$330.00 |
|
|
|
|
$230.00 |
$-100.00 |
|
|
Truck / tipping and cartage allowance
General |
Qty 1.00 allowance
|
$125.00 |
|
|
|
|
$125.00 |
$0.00 |
|
|
Backfilling and compaction allowance
Site Works |
Qty 1.00 allowance
|
$345.00 |
|
|
|
|
$450.00 |
$105.00 |
|
|
Additional labour allowance
General |
Qty 1.00 allowance
|
$450.00 |
|
|
|
|
$300.00 |
$-150.00 |
|
|
Truck and debris removal allowance
Waste |
Qty 1.00 hour
|
$200.00 |
|
|
|
|
$0.00 |
$-200.00 |
|
|
Backfill and topsoil allowance
Site Works |
Qty 1.00 allowance
|
$220.00 |
|
|
|
|
$120.00 |
$-100.00 |
|
|
Pipework allowance
Plumbing |
Qty 1.00 allowance
|
$500.00 |
|
|
|
|
$345.00 |
$-155.00 |
|
|
Plumber provision
Plumbing |
Qty 1.00 hour
|
$450.00 |
|
|
|
|
$412.50 |
$-37.50 |
|
|
Contingency allowance
General |
Qty 1.00 allowance
|
$500.00 |
|
|
|
|
$223.00 |
$-277.00 |
|
|